THE NEXT IMPORTANT PHASE IN THE CONSTRUCTION PROCESS IS FABRICATING
THE REBAR DIAPHRAGM, WHICH WILL SERVE TO REINFORCE THE SUB-GRADE
STRUCTURAL WALL AND TIE INTO THE SOLDIER PILES.

THIS PHASE IS SCHEDULED TO BEGIN ON TUESDAY, MAY 30, 2017

NEW ADDITIONS AS OF SUNDAY, June 4, 2017
(Click on the underlined titles, which
will take you directly to the post)

PPE: Hard Hats and Vests . . . Everybody Has to Wear ‘Em!

 Constructing the Sub-Grade Structural Wall

On o5.30.15, the following were added:

05.30.17 – 6

05.30.17 – 7 – Video

05.30.17 – 8

05.30.17 – 17

The Foundation: The Main Concrete Pours by Section

Added photo:

06.01.17 – 24

06.01.17 – 26

06.01.17 – 27

06.01.17 – 28

05.19.17 – 04

05.30.17 – 21

Elements of the Foundation: The Earthquake Damper System

05.23.17 – x

05.24.17 – x

06.01.17 – x Video

Featured Construction Photo

The final concrete pour 05.20.17

The Adventures of Pokemon
(NOTE: THIS STORY IS IN DRAFT FORM AND IS STILL BEING EDITED)

Hard Hats and Vests . . . Everybody Has to Wear ‘Em!

Photo 31 – 40

~

PLEASE NOTE:

SOME OF THE PHASES IN THE LLU CAMPUS TRANSFORMATION PROJECT

HAVE BEEN COMPLETED. THE TITLE OF THOSE POST WILL BE

MARKED *COMPLETED* AFTER THE TITLE. 

 

Share This
Dennis E. Park, MA
After graduate school Dennis accepted a position at Loma Linda University. He worked there for 42 years in the areas of administration and financial management, also teaching accounting and management to dietetic students at the School of Public Health. Through the years Dennis has chronicled the growth of the campus, including the construction of the Drayson Center and the Centennial Complex and the razing of Gentry Gym. He is the author of "The Mound City Chronicles: A Pictorial History of Loma Linda University, A Health Sciences Institution 1905 - 2005." dEp 09.30.2016 🔨
10 Comments
    • Dennis Schall

    Dennis, Are they digging a tunnel over at P4?

      • Dennis E. Park, MA

      Thanks for the question. No, they are putting in a drainage system that goes under the new parking lot to the east of P4. Stay tuned, I will be putting up photos of the area where the pipes will go in.

      dEp

        • Dennis Schall

        Thanks Dennis

    • Dennis Schall

    Dennis, are there any women on this construction crew. I have been seeing are men in the pictures.

      • Dennis E. Park, MA

      Yes, there is one female by the name of Liz and her photograph appears in the section: Portraits: To Those Who Get the Job Done. She works days and an occasional night shift. She is a very competent worker and is respected by the crew. She drives heavy equipment, uses power tools, takes her turn at guarding the gates when they are open. Of course there are women who work in the trailer offices, but she is the only female that is not afraid to get her hands dirty. Good Question.

    • Dennis Schall

    I think Pokemon moved again.

      • Dennis E. Park, MA

      Pokemon has been very busy. He is a VERY hard worker. Check his section out!

      • Dennis E. Park, MA

      Pokemon has been a VERY busy worker. I forced him to post some photos so that you could see how busy he has been. He promises, more are to follow.

    • Dennis Schall

    Dennis, A page that might be cool to have is Tools used on the project. you have shown a few already such as that the device on the dozer that measured grade.

      • Dennis E. Park, MA

      I will do my best. Thanks for the suggestion.