The Pit–In Memoriam Construction Site, Construction Techniques, Construction Update Vision 2020, Down in the Pit
Construction Site, Current Updates, People, Preliminary Work, Weekly Construction Blog The Week of May 20, 2018–The Podium Level Reached; Section Four Rises From the Pit On Sunday, May 20, 2018, the iron workers began hanging steel for the podium roof on the west side of the building. The feature photo... Read More
Campus History The Week of May 13, 2018–A New Crane Also Named “Cheese” This week we celebrate the fact that the concrete foundation floor is no longer visible from grade, except down to the bottom of the moat,... Read More
Campus History Loma Linda University Campus Transformation Project: Progress Update as of May 13, 2018 Now that the steel columns are visible rising well above the security fence, it is time to take a reality check on the Loma Linda... Read More
Campus History The Week of May 7, 2018–What a Week!!!!!! Cranes, Steel, and Concrete Floors The week began like any other week. We pretty much knew what the week would entail: cranes hoisting steel, welding, electrical, decking, rebar, pipefitting, and... Read More
Campus History The Week of April 30, 2018–The Foundation Steel For Section Four is Joined; Floors Three Through Five The week began On —————, 2017, the first of many double node spline beams was set in the northwest corner of the pit.... Read More