This page within the docuvision2020 website is a new blog that features the Barton Road Pedestrian Bridge (BRPB) construction. The bridge will link Parking Structure P4 on the south side of Barton Road to an Elevator Tower (presently under construction) on the north side of Barton Road near the southeast corner of the existing Children’s Hospital on the Dennis and Carol Troesh Medical Campus at Loma Linda University in Loma Linda, California. This project, benefiting patients, staff, and the general public, is a significant undertaking, which has been in the discussion and planning phases for many years.
Construction Timeline
Dennis, see the following information about the schedule for the Pedestrian Bridge over Barton Road:
Project started on October 28, 2020
Construction started on May 7, 2021.
Permitted by the City on June 9, 2021
Columns were completed on August 10, 2021
Concrete pre-cast beams were set November 22 and 23, 2021
Elevator construction started on December 1, 2021
Bridge Canopy construction began on December 6, 2021
Topping slab for bridge walkway will be poured (weather permitting) on December 15, 2021
State Inspection on the Elevator system is scheduled for January 31, 2022
Substantial completion of the project is projected near to February 2, 2022
Final Inspection with the City of Loma Linda is tentavely scheduled for February 2, 2022
BRPB Project completion date (weather permitting) is slated for March 1, 2022
Structural Information
4 Support Columns
6 pre cast beams
2 pre cast beams at the frontage road are 62 feet long and weight 78,000 pounds
2 pre cast beams over Barton Road at the west bound lane were 68 feet long and weight 85,500 pounds
2 pre cast beams over Barton Road at the east bound lane were 68’ long and weight 91,500 pounds
The bridge is on a 1% slope from the south to the north
The total span from parking structure P4 to the elevator tower is 225 feet
The measurement from Barton Road on the west bound lane to the bottom of the bridge is 16 feet 10 inches
The measurement from Barton Road on the east bound lane to the bottom of the bridge is 20 feet 8 inches
The beams are 5 feet tall and has a 4 feet thick walking surface.
The bridge will have a canopy roof over the complete distance
The width of the finished walking surface will be 8 feet 6 inches
The bridge will have metal panels which will enclose the side openings between the top of the beams and the canopy roof
2 over-the-road electronic message boards at 36 feet long and 6 feet 7 inches tall will be installed
The top of the elevator tower is 43 feet 4 inches tall from the east elevator door landing
The elevated deck is 26 feet 5 inches from the east elevator door landing
The elevated deck is covered completely
The elevator has 2 cars and three door landings
Current Status as of December 13, 2021
Work continues on the elevator tower. A crew is preparing the exterior for the three-step stucco process. Inside the elevator tower, Otis elevator is installing the structural steel that will support the elevator cars. The rebar has been installed on the landing stairs and the bridge walkway surface. If the weather cooperates, the four-inch concrete will be poured for the walkway surface on December 15, 2021. A crew from the company that will be installing the metal side panels and the roof is currently anchoring the support embeds which will hold the metal roof columns. According to the on-site supervisor, the crews have been instructed to keep moving forward.
About the Layout of this Blog
The BRPB images featured in the Dennis and Carol Troesh Medical Campus construction blog (the principal docuvision2020 blog) will remain in that blog. However, to keep the construction of the BRPB in context on this page, those images will flow onto this page. With few exceptions, I will post the photos in descending order by date. The images from August 13, 2021, until completion, will not be posted on the hospital page. THEY WILL ONLY BE POSTED ON THIS PAGE!
December 15, 2021 – The Walking Surface Concrete Pour
December 13, 2021 – UPDATE
November 12, 2021 – UPDATE
Thank you for continuing to visit the website. We’re back online again. Unfortunately, the site has had its hiccups of late. Hopefully, Hostgator has the problem resolved. I have been visiting the construction site and taking photos and I will be posting the most interesting images over this weekend. With the columns finished, the construction crew has been concentrating on the elevator tower, hanging steel, and installing the stairs in preparation for the beams to arrive. NOTE: ON NOVEMBER 22 – 24 BARTON ROAD WILL BE CLOSED TO TRAFFIC AT CAMPUS STREET AND ANDERSON STREET. On those dates, heavy cranes will be on-site to install the beams that will cross over Barton Road. This should be an exciting event!
November 24, 2021 – The Bridge Build, The Day After
November 23, 2021 – The Bridge Build Continues
More Photo to be Posted
November 22, 2021 – The Bridge Build Begins
November 18, 2021
November 16, 2021
November 10,2021
November 09, 2021
October 01, 2021
September 24, 2021
September 22, 2021
September 20, 2021
September 13, 2021
August 13, 2021
All Images Below Flow Through the Hospital Construction Page to This Page