With the Ramps Gone, How Does the Heavy Equipment Make it in and Out of the Pit?

With the Ramps Gone, How Does the Heavy Equipment Make it in and Out of the Pit?

03.06.17
On March 6, 2017, work began to excavate the ramp that served as the “road” to the bottom of the pit. Early on in the construction
process, there was no need for a ramp. As the pit got deeper a ramp was required and over time the dirt ramp had to be moved three times.
Even while the ramp was operational two cranes were used to transport the rebar from the trucks to the floor of the pit.

03.06.18
Excavation of the last ramp, which was the only access in and out of the pit. From now on cranes will be used to deliver materials and supplies down into the pit. Cranes will also be used for the transport of heavy equipment in and out of the pit.

03.06.19
A short clip from another angle of the last ramp being excavated. Note the grade to the ramp.

03.17.20
On March 6, 2017, work began to excavate the ramp that served as the “road” to the bottom of the pit. Early on in the construction

03.20.21
A tractor is carried by crane to the eastern grade above.

03.23.22
When there was a ramp a driver in a pickup truck would deliver the supplies to the pit below. Now that the ramp is gone, the task must be

accomplished by a crane.

03.23.23

Even a large stack of 4 x 8 plywood receives a crane ride down to the rat slab below.

03.24.24

The concrete finishing machines that are so vital to the upcoming big concrete pour are tethered together for the crane ride to the pit below.

04.04.17 – 25
A large telescopic crane above the south shoring wall carefully lowers a snorkel boom lift to the foundation mat. A lift on the mat preceded the
one being lowered. Parking structure P4, which is located on the south side of Barton Road is in the background.

04.04.17 – 26
A closeup of the snorkel boom lift being lowered to the foundation mat.

04.04.17 – 27
Next to be lowered is a 4 x 4 scissor lift.

Share This
Dennis E. Park, MA
After graduate school Dennis accepted a position at Loma Linda University. He worked there for 42 years in the areas of administration and financial management, also teaching accounting and management to dietetic students at the School of Public Health. Through the years Dennis has chronicled the growth of the campus, including the construction of the Drayson Center and the Centennial Complex and the razing of Gentry Gym. He is the author of "The Mound City Chronicles: A Pictorial History of Loma Linda University, A Health Sciences Institution 1905 - 2005." dEp 09.30.2016 🔨