The PROTOTYPE That Served a Purpose
If you have been at the intersection of Barton Road and Anderson Street sometime during the last 15 months, you might of seen it rising just above the security fence as illustrated in the feature image. The building, not much larger than a two story garage has generated some speculation. One of the most plausible suggestions is that the structure is the first section of the Children’s Hospital to be completed. To end the speculation, this post will take the reader behind the security fence and unveil the mystery building known as the prototype or mock-up.
In the latter part of 2017, laborers began to dig footings near the southeast section of the construction site near the corner of Barton Road and Anderson Street. The location was at the quarter turn of the sometimes paved one-lane gravel road on which the heavy construction equipment rumbled from one side of the construction site to the other.
The Site in the Bend of the Road Where the Prototype Would be Built
I assumed that the digging was for a concrete pad to support another electrical transformer. My supposition, made sense as there were a number of transformers in the area. I knew more transformers would be coming in to be set on the pads that had been poured. few days later as I made my rounds, I noticed the footings were more substantial than the ones for the electrical pads.
Its Construction
My suspicions were confirmed after the concrete forms were removed. This concrete pad was not like the other transformer pads. It appeared to be a foundation for some sort of structure. Why only three sides? I mused. A few days later, I inquired of a laborer working around the area if he knew anything about the concrete foundation. “All, I know,” he replied, “it is for a prototype or something.” With that bit of information, he walked toward the metal storage sheds pushing a wheelbarrow full of tools. Not knowing much more than before asking the question, I continued making my rounds.
As I rounded the turn a couple of days later, I noticed there had been some activity around the concrete pad. It was evident Iron worker had been there erecting steel columns and setting still beams. The steel wasn’t large, but it was apparent that whatever was being built needed to support some weight.
In the next few days more steel was added, precisely and strategically, to areas that would support the weight of the yet to be revealed prototype.
A few days later the iron workers returned and completed the steel frame: At least all the steel lying in the yard was gone. But there seemed to be a problem, three quarters of the north side was lacking steel. What kind of structure could this be? Could this be all there is to the skeleton of the prototype? I wondered to myself.
For a number of days there was no activity around the steel frame at the crook of the quarter turn. Then, two days after Christmas a different crew showed up with two slabs of what I thought might be lite beige of concrete panels.
The lite beige panels of concrete turned out to be GFRC (Glass fiber Reinforced Concrete) panels, so I was told by the one of the assistant job superintendents, who also explained the panels were samples of the GFRC exteriors that would be installed on the steel frame of the hospitals. These two panels were the beginning of the prototype….
. . . . of how the exterior of the new hospitals would appear when completed. It was also explained to me that such prototypes were now common place for owners and contractors to partner because in the end such prototypes or mock-ups saves money and time. I was told that these prototypes can cost the owner anywhere between a quarter and a half million dollars. Prototypes allow the various subcontractors, who in many cases have not worked with each other or worked with the materials that the architects and or engineers have specified. The materials mock-ups allow the contractors to determine how the various materials and fixtures connect together and how they react to the elements once installed. Periodic tests allow the contractors to make adjustments prior to the final fabrications and/or before installation, thus saving valuable time and money.
Eleven days into the the new year (2018) more panels had been added to the frame. In retrospect, I now see the GFRC panels used in the prototype now being installed on the structural frame of the current project.
I soon leaned that the mock-up did not apply solely with the exterior. Such testing including some interior applications as well.
As the days progressed, I noticed more material and fixtures being added to the mock-up. The interior corner framed with metal studs appeared to be a mock-up of how corners were framed with drywall hung.
it is amazing to me the different archetercial styles in the building. I think i count 6
You are correct, I will be posting something about the styles maybe even today. Thanks for noticing. I think the styes make the project a bit more interesting.
dEp